News

»

,

Upgrade Update #7

View of cable and hose reels from above in the drill tower.
Kurt Studt, IceCube/NSF

They’re getting close to drilling at the South Pole. Last week saw a continued influx of IceCube personnel, including some drillers and integration experts. The week’s primary focus was taking stock and working on final tasks in each work area. Crews tested the brakes on the large reel for the main drill cable, which is the orange cable seen above in a view from the drill tower. Others worked on hanging the drill head in the operations tower, connecting water hoses to two large tanks, and practicing module installation at the test hole. At the end of the week, they held a readiness review to compile a “punch list” of final items to complete before drilling begins.

Tower operations on the left, with drill supply hose and module testing facility on the right.
Kurt Studt, IceCube/NSF
Two people facing camera as they connect water hoses out on the ice.
Kurt Studt, IceCube/NSF
Vivian O’Dell, IceCube/NSF
Vivian O’Dell, IceCube/NSF
Andreas Noell, IceCube/NSF
Andreas Noell, IceCube/NSF

You may also be interested in…

  • Upgrade Update #9

    Colton Hill, IceCube/NSF

    Last week, the IceCube crew completed the drilling and installation for the first of the IceCube Upgrade strings. Above is a group of drillers on the day shift after deploying more than half of the modules into the hole. By the end of the week, they had begun drilling for the next …

  • First field season for IceCube Upgrade ongoing at the South Pole

    Over the past two months, a team of IceCube drill engineers have completed an impressive amount of work during the first of three consecutive field seasons for the IceCube Upgrade. The project is funded by the National Science Foundation and international collaborators.
    The goal of the project is to drill seven holes in 2025/2026 and deploy …

  • Upgrade Update #5

    Kurt Studt, IceCube/NSF

    The IceCube Upgrade project’s progress report for last week has earned the name, as “progress” smoothly continues. The drill camp now has two tower operations sites. One will serve as the installation practice site. The image above is a view looking down from one of the towers, with the wrapped-up drill supply …