News

»

,

Upgrade Update #11

Close-up on digital optical module.
Yuya Makino, IceCube/NSF

Steady progress continues on the IceCube Upgrade construction effort. Drilling and installation operations have continued to stabilize, and four of the seven holes have been completed so far. It takes a lot of energy to accomplish tasks at each stage of the process, from heavy lifting by equipment to position the tower operations structures to heavy lifting by crew members in moving large supply hoses and locating main cable reels used in installation. Last week, some IceCubers had enough excess energy to compete in the South Pole marathon.
 

Junction box out on the ice, open and displaying the cable connections.
Erik Blaufuss, IceCube/NSF
Large coil of cable in slack pit in the ice.
Erik Blaufuss, IceCube/NSF

You may also be interested in…

  • Upgrade Update #12

    Colton Hill, IceCube/NSF

    Last week the Upgrade team finished drilling the fifth hole and started in on the sixth. But it’s not all drilling for the team—there’s also installation of modules and then commissioning all the deployed devices. But there was progress on all fronts. The fifth string was completely deployed, and the commissioning team has …

  • Upgrade Update #10

    Yuya Makino, IceCube/NSF

    Three down, four to go. That’s IceCube Upgrade strings, in case you’ve missed the progress so far. Compared to the first hole, the second and third holes showed marked improvement in drilling time as well as somewhat improved overall installation times. The top photo shows a closeup of an mDOM as it …

  • Upgrade Update #5

    Kurt Studt, IceCube/NSF

    The IceCube Upgrade project’s progress report for last week has earned the name, as “progress” smoothly continues. The drill camp now has two tower operations sites. One will serve as the installation practice site. The image above is a view looking down from one of the towers, with the wrapped-up drill supply …